Platform 1 at Surat railway station will close for 80 days from December so that it can be broken down and rebuilt. For that period, 139 trains heading towards Ahmedabad, Rajasthan and Delhi will not stop at Surat. Of these, 89 will halt at Udhna and 50 at Utran, Gujarat Samachar reported.
The Railway Board has approved the block, the paper said. Western Railway has not yet named the starting date. Its chief public relations officer told the paper the date would be fixed within a week and passengers told in advance.
Which trains move to Udhna and which to Utran
Udhna is the junction south of Surat station; Utran lies to its north. The trains named so far are all northbound services from Mumbai. Lists published by Gujarat Samachar and GSTV include these:
- Halting at Udhna (89 trains, on Udhna’s Platform 1): Avantika Express (12961), Gujarat Express (22953), Bhuj AC Superfast (22903), Dehradun Express (19019), Bandra-Jaipur Express (19724) and Valsad-Haridwar Express (12911).
- Halting at Utran (50 trains): Lok Shakti Express (19017), Saurashtra Mail (22945), Gujarat Queen (19033), Bandra-Jamnagar Humsafar (22923) and Pune-Ahmedabad Ahimsa Express (22186).
- Still at Surat, on Platform 2 (44 trains): the Mumbai Central-Gandhinagar and Mumbai Central-Ahmedabad Vande Bharat trains (20901, 22961), Shatabdi Express (12009), Tejas Rajdhani (12951), August Kranti Tejas (12953) and the Double Decker Express (12931).
The full list of 139 trains has not been published in these reports. Passengers already booked from Surat on one of these trains should check the boarding station on the ticket or the railway enquiry app before leaving home. Short-distance trains that start or end at Surat will also see changes, DeshGujarat reported, without naming them.
Day by day: what the 80 days are for
The block is part of the Multi-Modal Transportation Hub (MMTH) project, which is rebuilding the station with a concourse above the tracks. The two Gujarati outlets give the same schedule:
- Days 1 to 10: shops, hoardings and electrical fittings come off Platform 1, and foundations for the overhead wiring are prepared.
- Days 11 to 25: the platform is barricaded. Its roof, shed, stalls and water lines are pulled down and underground services laid.
- Days 26 to 62: civil and structural work, and the launching of the concourse beams and columns.
- Days 62 to 80: finishing work and restoring the platform.
Trains will keep running on the track beside Platform 1 through the work, at a 20 kmph speed limit, according to DeshGujarat. They will pass through without picking up passengers there.
The last block at Surat ran 23 days over
Surat passengers have been through this before. Platforms 2 and 3 were closed from January 8, 2025 for a planned 60 days, and 201 trains were moved to Udhna. That block was extended to March 31 after the project company, SITCO, asked the railway for 23 more days to finish the concourse foundations.
This time Utran takes a share of the load, where the 2025 diversions went to Udhna alone.
The project itself is about half built. In September, SITCO put Phase 1, the station building and concourse, at 51% complete. The whole hub is expected by December 2027, DeshGujarat reported then. Phase 1 is costed at Rs 877.78 crore. The same update said work on the concourse between Platforms 1 and 2 would begin after the Diwali rush. The December block is that work.
Sources: Gujarat Samachar, GSTV, DeshGujarat